Yes. The Town of Milton issues residential permits for additions, alterations, secondary suites and new houses.
Not sure? Ask the Town before you start. Electrical work is reported to the Electrical Safety Authority, not the municipality.
From the Town's residential permit checklist. Applications missing items may not be accepted.
Every building on the lot, setbacks to all property lines, lot coverage, the driveway, and the septic and well if there is one.
Existing and new grades, top of foundation, footing and floor elevations, swales and the direction water drains.
Floor plans, elevations, wall sections and spatial separation calculations for the existing house and the addition.
Over 25% of the heated area: a design for the whole house. 10% to 25%: the addition. Under 10%: outlet sizes and locations on the drawings.
The application, the Schedule 1 designer form, a water pipe sizing form and the energy efficiency design summary.
On septic, needed when the addition grows the floor area by more than 15%, adds a bedroom or adds fixtures.
Residential permits go through the Town's online services portal.
Upload PDFs straight from the design software. Files over 10 MB need a secure link from the Town.
The Town emails to say the application is accepted or refused, then sends the invoice.
Starts once fees are paid. 10 business days for a complete house application.
The Town emails when the permit is ready.
Nothing gets covered until the inspector passes it.

Some lots need sign-off from another agency before the Town issues the building permit.
Yes. Additions of any size need a building permit from the Town of Milton.
Online through the Town's online services portal, with PDF drawings and forms.
The Town's posted fee for a new house or addition is $25.13 per square metre, with a $264.20 minimum. Check the current rate with the Town before you budget.
The Building Code gives 10 business days for a complete house application, once fees are paid.
Only if the lot is in a regulated area, such as near a creek or valley. The Town's checklist lists it as an approval to get first.
The Electrical Safety Authority, separate from the Town's building permit.
A site visit shows what your lot allows and what an addition would involve.